TFij= {(LCij - ESij) - Dij} |
Note that since activity i-j comes out of Node i and goes in to Node j, by definition, LCij=LCj and ESij=ESi
Critical Activity:
One that has a total float equal to 0, i.e.,
activity
i-j is critical if TFij=0. Note that TFij=0
(LCij - ESij)
= Dij, i.e., ESij + Dij = LCij.
Thus, a critical activity has no excess time available
for its completion
- it MUST start as soon as possible (at ESij) so that
it is
done no later than the time beyond which the project will be
delayed (LCij).
Critical Path:
A path of critical actvities in the project
network that
link the start node (Node 1) and the end node (Node n).
It is possible
for a project to have more than one critical path!
CPM: Critical Path Method
Continue
with next page...
Back
to previous page...