DEFINITIONS
Earliest Start Time for Node j (ESj):
Earliest time at which activities coming out
of
Node j can start (or equivalently, the earliest time by
which all
activities coming in to Node j can be
completed):
ESj= Maxi {ESi + Dij} for all defined activities i-j |
Latest Completion Time for Node i (LCi):
Latest time by which activities coming in
to Node
i
must be completed in order that the project be completed in its
minimum
duration (or equivalently, the latest time by which all
activities coming
out
of Node i must start so that the project's completion is
not delayed):
LCi=
ESi if i=n (the terminal node) Minj {LCj - Dij} for all defined activities i-j, if i¹ n |
EXAMPLE:
Consider the part of a network shown below with
activity
durations above the arcs. Focus on Node j=4.
ES4= (=ES4-5=ES4-6=ES4-7)
4 + 4 (=ES1+D14)
6 + 3 (=ES2+D24)
4 + 6 (=ES3+D34)
Thus ES4=Max{8,9,10} = 10
Next focus again on Node i=4.
LC4= (=LC1-4=LC2-4=
LC3-4)
18 - 3 (=LC4-D14)
17 - 5 (=LC5-D15)
15 - 4 (=LC6-D16)
Thus LC4=Min{15,12,11} = 11